Orion Petroleum (ASX: OIP) has reported that the Toenda-1 exploration well (licence PEL 6) in northern New South Wales, spudded on Sunday, 11 April 2010.
As at the morning report of 13 April, the well had been drilled to a depth of 509m. The current operation is running 9 5/8” casing.
Following cementing, nippling up the BOP’s and pressure testing, the company said the forward plan is to drill ahead in 8 ½” hole.
Orion said the primary objective Permian Upper Back Creek sandstone is prognosed to be intersected at around 1,360m. The planned total depth for Toenda-1 is 1,850m.
Orion has a 97.5% interest in PEL 6 with the remaining 2.5% held by private interest holders.
http://www.proactiveinvestors.com.au/companies/news/6401/orion-petroleum-updates-progress-on-toenda-1-oil-and-gas-well-6401.html
Thursday, 15 April 2010
Orion Petroleum updates progress on Toenda-1 oil and gas wellOrion Petroleum (ASX: OIP) has reported that the Toenda-1 exploration well (licence PEL 6) in northern New South Wales, spudded on Sunday, 11 April 2010. As at the morning report of 13 April, the well had been drilled to a depth of 509m. The current operation is running 9 5/8” casing. Following cementing, nippling up the BOP’s and pressure testing, the company said the forward plan is to drill ahead in 8 ½” hole. Orion said the primary objective Permian Upper Back Creek sandstone is prognosed to be intersected at around 1,360m. The planned total depth for Toenda-1 is 1,850m. Orion has a 97.5% interest in PEL 6 with the remaining 2.5% held by private interest holders.
Subscribe to:
Post Comments (Atom)
No comments:
Post a Comment